Mcqmate logo

270+ Operations Research Solved MCQs

1.
A. objective function
B. decision variable
C. constraints
D. opportunity cost
Answer» A. objective function
2.
A. infeasible region
B. unbounded region
C. infinite region
D. feasible region
Answer» D. feasible region
3.
A. outgoing row
B. key row
C. basic row
D. interchanging row
Answer» C. basic row
4.
A. dummy
B. epsilon
C. penalty
D. regret
Answer» B. epsilon
5.
A. ncwr
B. lcm
C. vam
D. hungarian
Answer» D. hungarian
6.
A. head path
B. sub path
C. critical path
D. sub critical path
Answer» C. critical path
7.
A. 7
B. 10
C. 18
D. 8
Answer» B. 10
8.
A. interfering float = total float – free float
B. total float =free float + independent float
C. total float ≥ free float ≥ independent float
D. free float = total float – head event slack
Answer» B. total float =free float + independent float
9.
A. expected
B. pessimitic
C. optimistic
D. most likely
Answer» C. optimistic
10.
A. processing order
B. idle time
C. processing time
D. elapsed time
Answer» D. elapsed time
11.
A. physical
B. symbolic
C. deterministic
D. probabilistic
Answer» C. deterministic
12.
A. physical
B. symbolic
C. deterministic
D. probabilistic
Answer» D. probabilistic
13.
A. cpm and pert
B. assignment & transportation
C. game theory
D. decision theory & inventory models
Answer» A. cpm and pert
14.
A. objective function
B. decision variables
C. constraints
D. opportunity cost
Answer» B. decision variables
15.
A. objective function
B. decision variables
C. constraints
D. opportunity cost
Answer» A. objective function
16.
A. objective function
B. variables
C. constraints
D. profit
Answer» C. constraints
17.
A. infeasible
B. unbounded
C. improper
D. unknown
Answer» A. infeasible
18.
A. less than or equal to
B. greater than or equal to
C. mixed
D. equal to
Answer» D. equal to
19.
A. infeasible
B. infinite
C. unique
D. degenerate
Answer» B. infinite
20.
A. key column
B. incoming column
C. important column
D. variable column
Answer» A. key column
21.
A. vital element
B. important element
C. basic element
D. key element
Answer» D. key element
22.
A. surplus
B. artificial
C. slack
D. additional
Answer» C. slack
23.
A. null resource
B. scarce resource
C. abundant resource
D. zero resource
Answer» B. scarce resource
24.
A. either zero or positive
B. either zero or negative
C. only positive
D. only negative
Answer» A. either zero or positive
25.
A. vogel’s approximat ion method
B. nwcr
C. lcm
D. modi
Answer» C. lcm
26.
A. infeasible solution
B. feasible solution
C. optimum solution
D. degenerate solution
Answer» B. feasible solution
27.
A. infeasible solution
B. feasible solution
C. non degenerate solution
D. degenerate solution
Answer» C. non degenerate solution
28.
A. vam
B. nwcr
C. modi
D. lcm
Answer» A. vam
29.
A. balanced
B. unbalanced
C. infeasible
D. unbounded
Answer» B. unbalanced
30.
A. vam
B. nwcr
C. modi
D. hungarian
Answer» D. hungarian
31.
A. cost
B. regret
C. profit
D. dummy
Answer» B. regret
32.
A. critical
B. sub-critical
C. best
D. worst
Answer» A. critical
33.
A. tentative
B. definite
C. latest
D. earliest
Answer» C. latest
34.
A. machines order
B. job order
C. processing order
D. working order
Answer» C. processing order
35.
A. processing
B. waiting
C. free
D. idle
Answer» D. idle
36.
A. objective function
B. decision variables
C. constraints
D. opportunity cost
Answer» C. constraints
37.
A. less than
B. greater than
C. not greater than
D. not less than
Answer» A. less than
38.
A. infeasible
B. infinite
C. unbounded
D. feasible
Answer» D. feasible
39.
A. multiple constraints
B. infinite constraints
C. infeasible constraints
D. mixed constraints
Answer» D. mixed constraints
40.
A. outgoing row
B. key row
C. interchanging row
D. basic row
Answer» B. key row
41.
A. null resource
B. scarce resource
C. abundant resource
D. zero resource
Answer» C. abundant resource
42.
A. unit price
B. extra price
C. retail price
D. shadow price
Answer» D. shadow price
43.
A. either zero or positive
B. either zero or negative
C. only positive
D. only negative
Answer» B. either zero or negative
44.
A. vogel’s approximat ion method
B. nwcr
C. lcm
D. modi
Answer» A. vogel’s approximat ion method
45.
A. dummy
B. penalty
C. regret
D. epsilon
Answer» D. epsilon
46.
A. there is no degeneracy
B. degeneracy exists
C. solution is optimum
D. problem is balanced
Answer» A. there is no degeneracy
47.
A. dummy
B. non-critical
C. important
D. critical
Answer» D. critical
48.
A. one
B. zero
C. highest
D. equal to duration
Answer» B. zero
49.
A. optimistic
B. pessimistic
C. expected
D. most likely
Answer» A. optimistic
50.
A. processing time
B. waiting time
C. elapsed time
D. idle time
Answer» C. elapsed time

Done Studing? Take A Test.

Great job completing your study session! Now it's time to put your knowledge to the test. Challenge yourself, see how much you've learned, and identify areas for improvement. Don’t worry, this is all part of the journey to mastery. Ready for the next step? Take a quiz to solidify what you've just studied.

Assignment Problem: Meaning, Methods and Variations | Operations Research

assignment problem in operations research mcq

After reading this article you will learn about:- 1. Meaning of Assignment Problem 2. Definition of Assignment Problem 3. Mathematical Formulation 4. Hungarian Method 5. Variations.

Meaning of Assignment Problem:

An assignment problem is a particular case of transportation problem where the objective is to assign a number of resources to an equal number of activities so as to minimise total cost or maximize total profit of allocation.

The problem of assignment arises because available resources such as men, machines etc. have varying degrees of efficiency for performing different activities, therefore, cost, profit or loss of performing the different activities is different.

Thus, the problem is “How should the assignments be made so as to optimize the given objective”. Some of the problem where the assignment technique may be useful are assignment of workers to machines, salesman to different sales areas.

Definition of Assignment Problem:

ADVERTISEMENTS:

Suppose there are n jobs to be performed and n persons are available for doing these jobs. Assume that each person can do each job at a term, though with varying degree of efficiency, let c ij be the cost if the i-th person is assigned to the j-th job. The problem is to find an assignment (which job should be assigned to which person one on-one basis) So that the total cost of performing all jobs is minimum, problem of this kind are known as assignment problem.

The assignment problem can be stated in the form of n x n cost matrix C real members as given in the following table:

assignment problem in operations research mcq

Operations Research Questions and Answers – MCQ Quiz

Operations Research Questions & Answers

Operations Research  Online Quiz Following  quiz  provides Multiple Choice  Questions (MCQs) related to OS . You will have to read all the given answers and click on the view answer option.

These HTML online test quizzes on Operations Research have answers available with pdf, which is very useful in interviews and also in HTML subject exams.

Question 1: Operations Research approach is?

(A) multi-disciplinary

(B) scientific

(C) intuitive

(D) collect essential data

Question 2: Operation research approach is typically based on the use of ___________.

(A) physical model

(B) mathematical model

(C) iconic model

(D) descriptive model

Question 3: Mathematical model of linear programming problem is important because ___________.

(A) it helps in converting the verbal description and numerical data into a mathematical expression

(B) decision-makers prefer to work with formal models

(C) it captures the relevant relationship among decision factors

(D) it enables the use of algebraic technique

Question 4: In Program Evaluation Review Technique for an activity, the optimistic time 2, the pessimistic time is 12 and most likely time is 4. What is the expected time?

Question 5: Graphical method of linear programming is useful when the number of decision variable are __________.

(D) infinite

Question 6: A feasible solution to a linear programming problem _______________.

(A) must satisfy all the constraints of the problem simultaneously

(B) need not satisfy all of the constraints, only some of them

(C) must be a corner point of the feasible region.

(D) must optimize the value of the objective function

Question 7: Utilization factor is also known as ___________.

(A) Traffic intensity

(B) Kendals notation

(C) Row minima method

(D) Unbalanced assignment problem

Question 8: While solving a linear programming problem infeasibility may be removed by _________.

(A) adding another constraint

(B) adding another variable

(C) removing a constraint

(D) removing a variable

Question 9: In the optimal simplex table, Zj-Cj=0 value indicates _____________.

(A) alternative solution

(B) bounded solution

(C) infeasible solution

(D) unbounded solution

Question 10: If all aij values in the entering variable column of the simplex table are negative, then ___________.

(A) there are multiple solutions

(B) there exist no solution

(C) solution is degenerate

(D) solution is unbounded

Question 11: If an artificial variable is present in the basic variable column of optimal simplex table, then the solution is ___________.

(A) alternative

(B) bounded

(C) no solution

(D) infeasible

Question 12: For any primal problem and its dual ______________.

(A) optimal value of objective function is same

(B) primal will have an optimal solution if dual does too

(C) both primal and dual cannot be infeasible

(D) dual will have an optimal solution if primal does too

Question 13: Principle of complementary slackness states that ____________.

(A) primal slack*dual main=0

(B) primal main+dual slack=0

(C) primal main+dual surplus=0

(D) dual slack*primal main not equal to zero

Question 14: If primal linear programming problem has a finite solution, then dual linear programming problem should have ____________.

(A) finite solution

(B) infinite solution

(C) bounded solution

(D) alternative solution

Question 15: The initial solution of a transportation problem can be obtained by applying any known method. However, the only condition is that __________.

(A) the solution be optimal

(B) the rim conditions are satisfied

(C) the solution not be degenerate

(D) the few allocations become negative

Question 16: The dummy source or destination in a transportation problem is added to ______________.

(A) satisfy rim conditions

(B) prevent solution from becoming degenerate

(C) ensure that total cost does not exceed a limit

(D) the solution not be degenerate

Question 17: Which of the following methods is used to verify the optimality of the current solution of the transportation problem ____________.

(A) Modified Distribution Method

(B) Least Cost Method

(C) Vogels Approximation Method

(D) North West Corner Rule

Question 18: An optimal assignment requires that the maximum number of lines which can be drawn through squares with zero opportunity cost be equal to the number of ________.

(A) rows or coloumns

(B) rows and coloumns

(C) rows+columns- 1

(D) rows-columns

Question 19: Maximization assignment problem is transformed into a minimization problem by _____________.

(A) adding each entry in a column from the maximum value in that column

(B) subtracting each entry in a column from the maximum value in that column

(C) subtracting each entry in the table from the maximum value in that table

(D) adding each entry in the table from the maximum value in that table

Question 20: To proceed with the MODI algorithm for solving an assignment problem, the number of dummy allocations need to be added are ___________.

Question 21: An artificial variable leaves the basis means, there is no chance for the ________ variable to enter once again.

(B) surplus

(C) artificial

Question 22: Simplex method was designed by ___________.

(A) Dantzig

(B) A.Charnes

(D) Hungarian

Question 23: Dual Simplex Method was introduced by ____________.

Question 24: 4. The cell with allocation can be called ___________ .

(B) Empty cell

(C) Basic cell

(D) Non-basic cell

Question 25: The cell without allocation is called __________.

(A) Basic cell

(B) Non-basic cell

(C) Empty cell

(D) Basic solution

Question 26: Service mechanism in a queuing system is characterized by _____________.

(A) customers behavior

(B) servers behavior

(C) customers in the system

(D) server in the system

Question 27: . The problem of replacement is felt when job performing units fail _______________.

(A) suddenly and gradually

(B) gradually

(C) suddenly

(D) neither gradually nor suddenly

Question 28: Least Cost Method is also known as __________.

(A) North West Corner Method

(B) Matrix Minima Method

(C) Row Minima method

(D) Coloumn Minima method

Question 29: The objective of network analysis is to ___________.

(A) minimize total project duration

(B) minimize total project cost

(C) minimize production delays, interruption, and conflicts

(D) maximize total project duration

Question 30: A activity in a network diagram is said to be __________ if the delay in its start will further delay the project completion time.

(A) forward pass

(B) backward pass

(C) critical

(D) non critical

MCQs and Answers

Engineering interview questions, Mcqs, Objective Questions,Class Notes,Seminor topics,Lab Viva Pdf free download. CIVIL | Mechanical | CSE | EEE | ECE | IT | Chemical Online Quiz Tests for Freshers.

300+ TOP Operations Research MCQs and Answers Quiz

Operations research multiple choice questions.

1. The main objective of OR is to provide a ___, ___ to the decision-makers. Answer: Scientific basis

2. OR employs a team of ___ from ___ ___. Answer: Scientists, different disciplines

3. Mention two applications of OR. Answer: Industry Planning

4. How can a hospital benefit from the application of OR methods? Answer: To solve waiting for problems

5. OR ___ inter-disciplinary approach. Answer: Imbibes

6. OR increases the effectiveness of ___ ability. Answer: Decision making

7. OR gives a qualitative solution Answer: True

8. One of the OR phases is the Action phase Answer: True

9. Diagram belongs to the physical model Answer: True

10. Allocation problems are represented by the iconic model Answer: False

Operations Research MCQs

11. OR methodology consists of definition, solution and validation only. Answer: False

12. The interaction between the OR team and Management reaches peak level in the implementation phase. Answer: False

13. OR imbibes ___ team approach. Answer: Inter-disciplinary

14. Linear programming is the tool of ___. Answer: OR

15. The three phases of OR are ___. Answer: Judgement phase, Research phase & Action phase

16. To solve any problem through the OR approach the first step is ___. Answer: Define the problem

17. ___ represents a real-life system. Answer: Model

18. ___ represents the controlled variables of the system Answer: Parameters

19. Both the objective function and constraints are expressed in ___ forms. Answer: Linear

20. LPP requires existence of ___, ___, ___ and ___. Answer: An alternate course of action

21. Solution of decision variables can also be ____. Answer: Fractious

22. One of the characteristics of canonical form in the objective function must be of maximisation. Answer: True

23. 2x – 3y ≤ 10 can be written as -2x + 3y ≥-10 Answer: True

24. The collection of all feasible solutions is known as the ___ region. Answer: Feasible

25. A linear inequality in two variables is known as a ___. Answer: Half-plan

26. The feasible region is a convex set Answer: True

27. The optimum value occurs the anywhere infeasible region Answer: False

28. We add a surplus variable for “≤” of constraint. Answer: False

29. The right-hand side element of each constraint is non-negative. Answer: True

30. A basic solution is said to be a feasible solution if it satisfies all constraints. Answer: True

31. If one or more values of the basic variable are zero then the solution is said to be degenerate. Answer: True

32. The right-hand side element of each constraint is non-negative. Answer: Yes

33. The key column is determined by Zj – Cj row. Answer: Yes

34. Pivotal element lies on the crossing of the key column and key row. Answer: No

35. The negative and infinite ratios are considered for determining key row. Answer: Yes

36. The value of artificial value is “M”. Answer: Yes

37. Artificial variables enter as basic variables. Answer: Yes

38. Dual LPP always reduces the amount of computation. Answer: No

39. It is possible to reverse the dual LPP to primal LPP Answer: Yes

40. The coefficients of decision variables in the objective function become quantities on the right-hand side of ___. Answer: Dual

41. “≤” constraints changes to ___ type in dual LP. Answer: ≥

42. For every LPP, there exists a unique ___ problem. Answer: Dual

43. Dual variables represent the worth or unit of a resource. Answer: True

44. Optimality is reached when the resources are not fully utilised. Answer: False

45. At the optimum level the relationship holds as a strict equation Answer: True

46. Sensitivity analysis is carried out on ___ simplex table. Answer: Final

47. It helps us to study the effect of changes in ___ ___ in the objective function. Answer: Resource, levels

48. The results of sensitive analysis establish ___ and ___ ___ for input parameters value. Answer: Upper, lower, bounce

49. Transportation problems are a special type of ___. Answer: LPP

50. The number of rows and columns need not always be ___. Answer: Equal

51. Transportation problem develops a schedule at ___ and ___. Answer: Minimum cost

52. In transportation problems, ∑ai = ∑bj is a sufficient and necessary condition for getting a feasible solution. Answer: Yes

53. Transportation problems can also be solved by the simplex method. Answer: Yes

54. Matrix-minima method gives the optimum solution. Answer: No

55. In matrix-minima method, you start allocating from the left-top cell of the table. Answer: False

56. In Vogel‟s approximation method, you first construct penalty and then start allocating. Answer: True

57. North-west corner rule gives the optimum solution. Answer: False

58. Vogel‟s approximation method gives a solution near to the optimum solution. Answer: True

59. All the values of ΔCij – ui – vj should be ___ or ___ for the solution to be optimum. Answer: zero

60. In unbalanced transportation problem ∑ai is ___ ___ to ∑bj. Answer: Not equal to

61. If the number of allocation is less than ___ then it is said to be a degenerate transportation problem. Answer: m + n – 1

62. In an AP, the constraints are of equality type. Answer: True

63. The number of facilities should be equal to the number of resources. Answer: True

64. The decision variables can take on any value. Answer: False

65. In the Hungarian method, you prepare the row-reduced matrix. Answer: True

66. The number of assignments should be equal to the number of rows for an optimum solution. Answer: True

67. There can be more than one allocation in a row. Answer: False

68. In unbalanced AP, the number of rows ___ to the number of columns. Answer: ≠

69. Hungarian method cannot be applied directly to ___ problem. Answer: Maximisation problem

70. If some jobs cannot be assigned to some machines, then it is called ___ assignment problem. Answer: Infeasible

71. In the travelling salesman problem, the objective is to visit each city ___ ___. Answer: Only once

72. Salesman has ___ different sequences if n is the number of cities to be visited. Salesman Answer: (n-1)

73. Integer programming is applied to problems that involve discrete variables. Answer: True

74. If some variables take on non-negative values, then it is known as pure IPP. Answer: False

75. An optimum solution to IPP is first obtained by using ___. Answer: Simplex method

Operations Research MCQs

1. Operations research is the application of ____________methods to arrive at the optimal Solutions to the problems.

  • a and b both

2.    In operations research, the ——————————are prepared for situations.

  • mathematical models
  • physical models diagrammatic
  • diagrammatic models

3.    Operations management can be defined as the application of ————-to a problem within a system to yield the optimal solution.

  • Suitable manpower
  • mathematical techniques, models, and tools
  • Financial operations

4.   Operations research is based upon collected information, knowledge and advanced study of various factors impacting a particular operation. This leads to more informed —-

  • Management processes
  • Decision making

5.    OR can evaluate only the effects of ————————————————–.

  • Personnel factors.
  • Financial factors
  • Numeric and quantifiable factors.

6 Which of the following is not the phase of OR methodology?

  • Formulating a problem
  • Constructing a model
  • Establishing controls
  • Controlling the environment

7 – The  objective  function  and  constraints  are  functions  of  two  types  of  variables,

_______________ variables and ____________ variables.

  • Positive and negative
  • Controllable and uncontrollable
  • Strong and weak
  • None of the above

8 – Operations research was known as an ability to win a war without really going in to ____

  • Battle field
  • The opponent
  • Both A and B

9 – Who defined OR as scientific method of providing executive departments with a quantitative basis for decisions regarding the operations under their control?

  • Morse and Kimball (1946)
  • P.M.S. Blackett (1948)
  • E.L. Arnoff and M.J. Netzorg

10 – OR has a characteristics that it is done by a team of

  • Mathematicians
  • All of the above

MCQ on Operations Research

11 – A solution can be extracted from a model either by

  • Conducting experiments on it
  • Mathematical analysis
  • Diversified Techniques

12 OR uses models to help the management to determine its _____________

13 What have been constructed from OR problems an methods for solving the models that are available in many cases?

  • Scientific Models
  • Mathematical Models

14 -Which technique is used in finding a solution for optimizing a given objective, such as profit maximization or cost reduction under certain constraints?

  • Quailing Theory
  • Waiting Line
  • Linear Programming

15 -What enables us to determine the earliest and latest times for each of the events and activities and thereby helps in the identification of the critical path?

  • Programme Evaluation
  • Review Technique (PERT)
  • Deployment of resources

16 – OR techniques help the directing authority in optimum allocation of various limited resources like_____

  • Man and machine
  • all of the above

17 -The Operations research technique which helps in minimizing total waiting and service costs is

  • ueuing Theory
  • Decision Theory

18 .What is the objective function in linear programming problems?

  • A constraint for available resource
  • An objective for research and development of a company
  • A linear function in an optimization problem
  • A set of non-negativity conditions

19 – .Which statement characterizes standard form of a linear programming problem?

  • Constraints are given by inequalities of any type
  • Constraints are given by a set of linear equations
  • Constraints are given only by inequalities of >= type
  • Constraints are given only by inequalities of <= type

20 – Feasible solution satisfies __________

  • Only constraints
  • only non-negative restriction
  • [a] and [b] both
  • [a],[b] and Optimum solution

21 – In Degenerate solution value of objective function _____________.

  • increases infinitely
  • basic variables are nonzero
  • decreases infinitely
  • One or more basic variables are zero

22 – Minimize Z = ______________

  • maximize(Z)
  • maximize(-Z)
  • none of the above

23 -In graphical method the restriction on number of constraint is _________

  • not more than 3

24 -In graphical representation the bounded region is known as _________ region.

  • basic solution
  • feasible solution

25 -Graphical optimal value for Z can be obtained from

  • Corner points of feasible region
  • Both a and c
  • corner points of the solution region

26 -In LPP the condition to be satisfied is

  • Constraints have to be linear
  • Objective function has to be linear
  • both a and b

27 – Identify the type of the feasible region given by the set of inequalities

x – y <= 1

x – y >= 2

where both x and y are positive.

  • A rectangle
  • An unbounded region
  • An empty region

28 -Consider the given vectors: a(2,0), b(0,2), c(1,1), and d(0,3). Which of the following vectors are linearly independent?

  • a)  b, and c are independent
  • a, b, and d are independent
  • a and c are independent
  • b and d are independent

Q29 – Consider the linear equation

x1 + 3 x2 – 4 x3 + 5 x4 = 10

How many basic and non-basic variables are defined by this equation?

  • One variable is basic, three variables are non-basic
  • Two variables are basic, two variables are non-basic
  • Three variables are basic, one variable is non-basic
  • All four variables are basic

30 – The objective function for a minimization problem is given by

z = 2 x1 – 5 x2 + 3 x3

The hyperplane for the objective function cuts a bounded feasible region in the space (x1,x2,x3). Find the direction vector d, where a finite optimal solution can be reached.

  • d(-2,-5,-3)

31 – In game theory, the outcome or consequence of a strategy is referred to as the

  • end-game strategy.

32-  Operations Research approach is?

  • multi-disciplinary
  •  collect essential data

33 – Operation research approach is typically based on the use of _____

  • physical model
  •  mathematical model
  •  iconic model
  •  descriptive model

34 – Mathematical model of linear programming problem is important because ________

  • it helps in converting the verbal description and numerical data into mathematical expression
  • decision makers prefer to work with formal models
  •  it captures the relevant relationship among decision factors
  •  it enables the use of algebraic technique

35 –  In Program Evaluation Review Technique for an activity, the optimistic time 2, the pessimistic time is 12 and most-likely time is 4. What is the expected time?

36 – Graphical method of linear programming is useful when the number of decision variable are __________.

37 – A feasible solution to a linear programming problem _______________.

  • must satisfy all the constraints of the problem simultaneously
  •  need not satisfy all of the constraints, only some of them
  •  must be a corner point of the feasible region.
  •  must optimize the value of the objective function

38 – Utilization factor is also known as ___________.

  • Traffic intensity
  • Kendals notation
  • Row minima method
  • Unbalanced assignment problem

39 –  While solving a linear programming problem in feasibility may be removed by _________.

  • adding another constraint
  •  adding another variable
  •  removing a constraint
  • removing a variable

40 –  In the optimal simplex table, Zj-Cj=0 value indicates _____________.

  • alternative solution
  •  bounded solution
  •  infeasible solution
  •  unbounded solution

41 –  If all aij values in the entering variable column of the simplex table are negative, then ___________.

  • there are multiple solutions
  •  there exist no solution
  •  solution is degenerate
  •  solution is unbounded

42 –  If an artificial variable is present in the basic variable column of optimal simplex table, then the solution is ___________.

  • alternative
  • no solution

43 – For any primal problem and its dual ______________.

  • optimal value of objective function is same
  • primal will have an optimal solution iff dual does too
  •  both primal and dual cannot be infeasible
  •  dual will have an optimal solution iff primal does too

44 – Principle of complementary slackness states that ____________.

  • primal slack*dual main=0
  •  primal main+dual slack=0
  • primal main+dual surplus=0
  •  dual slack*primal main not equal to zero

45 – If primal linear programming problem has a finite solution, then dual linear programming problem should have ____________.

  • finite solution
  •  infinite solution
  • bounded solution
  •  alternative solution

46 – The initial solution of a transportation problem can be obtained by applying any known method. How-ever, the only condition is that __________.

  • the solution be optimal
  •  the rim conditions are satisfied
  •  the solution not be degenerate
  • the few allocations become negative

47 -The dummy source or destination in a transportation problem is added to ______.

  • satisfy rim conditions
  • prevent solution from becoming degenerate
  • ensure that total cost does not exceed a limit

48 – Which of the following methods is used to verify the optimality of the current solution of the transportation problem ____________.

  • Modified Distribution Method
  • Least Cost Method
  •  Vogels Approximation Method
  •  North West Corner Rule

49 – An optimal assignment requires that the maximum number of lines which can be drawn through squares with zero opportunity cost be equal to the number of ________.

  • rows or coloumns
  • rows and coloumns
  • rows+columns- 1
  • rows-columns

50 –  Maximization assignment problem is transformed into a minimization problem by ________.

  • adding each entry in a column from the maximum value in that column
  •  subtracting each entry in a column from the maximum value in that column
  • subtracting each entry in the table from the maximum value in that table
  •  adding each entry in the table from the maximum value in that table

51 –  To proceed with the MODI algorithm for solving an assignment problem, the number of dummy allocations need to be added are ___________.

52 – An artificial variable leaves the basis means, there is no chance for the ________ variable to enter once again.

53 –  Simplex method was designed by ___________.

54 – Dual Simplex Method was introduced by ____________.

55 – The cell with allocation can be called ___________ .

  •  Empty cell
  •  Basic cell
  • Non-basic cell

56 – The cell without allocation is called __________.

  •  Non-basic cell
  • Basic solution

57 – Service mechanism in a queuing system is characterized by ___

  • customers behavior
  •  servers behavior
  •  customers in the system
  •  server in the system

58 – The problem of replacement is felt when job performing units fail ____

  • suddenly and gradually
  •  neither gradually nor suddenly

59 – Least Cost Method is also known as __________.

  • North West Corner Method
  •  Matrix Minima Method
  •  Row Minima method
  • Coloumn Minima method

60 – The objective of network analysis is to ___________.

  • minimize total project duration
  •  minimize total project cost
  •  minimize production delays, interruption and conflicts
  •  maximize total project duration

61 – A activity in a network diagram is said to be __________ if the delay in its start will further delay the project completion time.

  • forward pass
  • backward pass
  • non critical

62 – A strategy that is best regardless of what rival players do is called

  • first-mover advantage.
  • a Nash equilibrium strategy.
  • tit-for-tat.
  • a dominant strategy.

63 – A game that involves interrelated decisions that are made over time is a

  • sequential game .
  • repeated game.
  • zero-sum game.
  • nonzero-sum game.

64 – A game that involves multiple moves in a series of identical situations is called a

  • sequential game.
  • repeated game .

65 – Sequential games can be solved using

  • dominated strategies.
  • backward induction
  • risk averaging.

66 – A firm that is threatened by the potential entry of competitors into a market builds excess production capacity. This is an example of

  • a prisoners’ dilemma.
  • a credible threat.

67 – What is the fundamental purpose of game theory?

  • To analyse decision-making
  • To analyse strategic interactions
  • To predict decision outcome
  • To predict firm behaviour

68 – An assignment problem is considered as a particular case of a transportation problem because

  • The number of rows equals columns
  • All xij= 0 or 1
  • All rim conditions are 1

69 – An optimal assignment requires that the maximum number of lines that can be drawn through squares with zero opportunity cost be equal to the number of

  • Rows or columns
  • Rows & columns
  • Rows + columns –1 d.

70 – While solving an assignment problem, an activity is assigned to a resource through a square with zero opportunity cost because the objective is to

  • Minimize total cost of assignment
  • Reduce the cost of assignment to zero
  • Reduce the cost of that particular assignment to zero

71 – The method used for solving an assignment problem is called

  • Reduced matrix method
  • MODI method
  • Hungarian method

72 – The purpose of a dummy row or column in an assignment problem is to

  • Obtain balance between total activities &total resources
  • Prevent a solution from becoming degenerate
  • Provide a means of representing a dummy problem

73 – Maximization assignment problem is transformed into a minimization problem by

  • Adding each entry in a column from the maximization value in that column
  • Subtracting each entry in a column from the maximum value in that column
  • Subtracting each entry in the table from the maximum value in that table
  • Any one of the above

74 – If there were n workers & n jobs there would be

  • n! solutions
  • (n-1)! solutions
  • (n!)nsolutions
  • n solutions

75 -An assignment problem can be solved by

  • Simplex method
  • Transportation method
  • Both a & b
  • none of above

76 – The assignment problem

  • Requires that only one activity be assigned to each resource
  • Is a special case of transportation problem
  • Can be used to maximize resources

Q77 – An assignment problem is a special case of transportation problem, where

  • Number of rows equals number of columns
  • Values of each decision variable is either 0 or 1

78 – Every basic feasible solution of a general assignment problem, having a square pay-off matrix of order, n should have assignments equal t

79 – To proceed with the MODI algorithm for solving an assignment problem, the number of dummy allocations need to be added are

80 – The Hungarian method for solving an assignment problem can also be used to solve

  • A transportation problem
  • A travelling salesman problem
  • A LP problem

MCQ on Operations Research 

81  An optimal solution of an assignment problem can be obtained only if

  • Each row & column has only one zero element
  • Each row & column has at least one zero element
  • The data is arrangement in a square matrix

82 – Which method usually gives a very good solution to the assignment problem?

  • northwest corner rule
  • Vogel’s approximation method

d) stepping-stone method

83 – The northwest corner rule requires that we start allocating units to shipping routes in the: middle cell.

  • Lower right corner of the table.
  • Upper right corner of the table.
  • Highest costly cell of the table.
  • Upper left-hand corner of the table.

84 – The table represents a solution that is:

  • an initial solution
  • degenerate.

85 – Which of the following is used to come up with a solution to the assignment problem?

  • northwest corner method
  • stepping-stone method

86 – What is wrong with the following table?

  • The solution is infeasible.
  • The solution is degenerate.
  • The solution is unbounded.
  • The solution is inefficient in that it is possible to use fewer routes.

87 –  The solution presented in the following table is

  • infeasible.

88 – The solution shown was obtained by Vogel’s approximation. The difference between the objective function for this solution and that for the optimal is

89 – Optimal solution of an assignment problem can be obtained only if

90 – In assignment problem of maximization, the objective is to maximise

  • optimization

91 – What is the difference between minimal cost network flows and transportation problems?

  • The minimal cost network flows are special cases of transportation problems
  • The transportation problems are special cases of the minimal cost network flows
  • There is no difference
  • The transportation problems are formulated in terms of tableaus, while the minimal cost network flows are formulated in terms of graphs

92 – With the transportation technique, the initial solution can be generated in any fashion one chooses. The only restriction is that

  • the edge constraints for supply and demand are satisfied.
  • the solution is not degenerate.
  • the solution must be optimal.
  • one must use the northwest-corner method

93 – The purpose of the stepping-stone method is to

  • develop the initial solution to the transportation problem.
  • assist one in moving from an initial feasible solution to the optimal solution.
  • determine whether a given solution is feasible or not.
  • identify the relevant costs in a transportation problem.

94 – The purpose of a dummy source or dummy destination in a transportation problem is to

  • prevent the solution from becoming degenerate.
  • obtain a balance between total supply and total demand.
  • make certain that the total cost does not exceed some specified figure.
  • provide a means of representing a dummy problem.

94 – Which of the following is NOT needed to use the transportation model?

  • the cost of shipping one unit from each origin to each destination
  • the destination points and the demand per period at each
  • the origin points and the capacity or supply per period at each

95 – Which of the following is a method for improving an initial solution in a transportation problem?

  • northwest-corner
  • intuitive lowest-cost
  • southeast-corner rule
  • stepping-stone

96 – The transportation method assumes that

  • there are no economies of scale if large quantities are shipped from one source to one destination
  • the number of occupied squares in any solution must be equal to the number of rows in the table plus the number of columns in the table plus 1.
  • there is only one optimal solution for each problem.
  • the number of dummy sources equals the number of dummy destinations.

97 – An initial transportation solution appears in the table.

  • Yes, this solution can be improved by $50.
  • Yes, this solution can be improved by $100.
  • No, this solution is optimal.
  • Yes, the initial solution can be improved by $10.

98 – What is the cost of the transportation solution shown in the table?

99 – Which statement regarding this transportation table is best?

  • This solution can be improved by shipping from C to X.
  • This solution would be improved by shipping from B to W.
  • This solution was developed using the northwest corner rule.

100 – Which of these statements about the stepping-stone method is best?

  • A dummy source and destination must be added if the number of rows plus columns minus 1 is not equal to the number of filled squares.
  • Only squares containing assigned shipments can be used to trace a path back to an empty square.
  • An improvement index that is a net positive means that the initial solution can be improved.
  • Only empty squares can be used to trace a path back to a square containing an assigned shipment

101 – In  a  transportation  problem,  we  must  make  the  number  of  _______  and______ equal.

  • destinations; sources
  • units supplied; units demanded
  • columns; rows
  • positive cost coefficients; negative cost coefficients

102 – _________ or __________ are used to “balance” an assignment or transportation problem.

  • Destinations; sources
  • Units supplied; units demanded
  • Dummy rows; dummy columns
  • Large cost coefficients; small cost coefficients

103 – The net cost of shipping one unit on a route not used in the current transportation problem solution is called the __________.

  • change index
  • Improvement index

104 – The procedure used to solve assignment problems wherein one reduces the original assignment costs to a table of opportunity costs is called __________.

  • matrix reduction
  • northwest reduction

105 – The method of finding an initial solution based upon opportunity costs is called__________.

  • the northwest corner rule
  • Vogel’s approximation
  • Johanson’s theorem
  • Flood’s technique

106 – An assignment problem can be viewed as a special case of transportation problem in which the capacity from each source is _______ and the demand at each destination is________.

  • Infinity; infinity

107 – _______ occurs when the number of occupied squares is less than the number of rows plus

  • Infeasibility
  • Unboundedness

108 – Both transportation and assignment problems are members of a category of LP problems called ______.

  • shipping problems
  • logistics problems
  • generalized flow problems
  • network flow problem

109 – The equation Ri + Kj = Cij is used to calculate __________.

  • an improvement index for the stepping-stone method
  • the opportunity costs for using a particular route
  • the MODI cost values (Ri, Kj)
  • the degeneracy index

110 – In case of an unbalanced problem, shipping cost coefficients of ______ are assigned to each created dummy factory or warehouse.

  • very high positive costs
  • very high negative costs

111 – The initial solution of a transportation problem can be obtained by applying any known method. However, the only condition is that

  • The solution be optimal
  • The rim conditions are satisfied
  • The solution not be degenerate

112 – The dummy source or destination in a transportation problem is added to

  • Satisfy rim conditions
  • Prevent solution from becoming degenerate
  • Ensure that total cost does not exceed a limit

113 – The occurrence of degeneracy while solving a transportation problem means that

  • Total supply equals total demand
  • The solution so obtained is not feasible
  • The few allocations become negative

114 – An alternative optimal solution to a minimization transportation problem exists whenever opportunity cost corresponding to unused route of transportation is:

  • Positive & greater than zero
  • Positive with at least one equal to zero
  • Negative with at least one equal to zero

115 – One disadvantage of using North-West Corner rule to find initial solution to the transportation problem is that

  • It is complicated to use
  • It does not take into account cost of transportation
  • It leads to a degenerate initial solution

116 – The solution to a transportation problem with ‘m’ rows (supplies) & ‘n’ columns (destination) is feasible if number of positive allocations are

117 – If an opportunity cost value is used for an unused cell to test optimality, it should be

  • Equal to zero
  • Most negative number
  • Most positive number

118 – During an iteration while moving from one solution to the next, degeneracy may occur when

  • The closed path indicates a diagonal move
  • Two or more occupied cells are on the closed path but neither of them represents a corner of the path.
  • Two or more occupied cells on the closed path with minus sign are tied for lowest circled value
  • Either of the above

119 – The large negative opportunity cost value in an unused cell in a transportation table is chosen to improve the current solution because

  • It represents per unit cost reduction
  • It represents per unit cost improvement
  • It ensure no rim requirement violation

120 – The smallest quantity is chosen at the corners of the closed path with negative sign to be assigned at unused cell because

  • It improve the total cost
  • It does not disturb rim conditions
  • It ensure feasible solution

121 – When total supply is equal to total demand in a transportation problem, the problem is said to be

122 – Which of the following methods is used to verify the optimality of the current solution of the transportation problem

  • Least cost method
  • Modified distribution method

123 – The degeneracy in the transportation problem indicates that

  • Dummy allocation(s) needs to be added
  • The problem has no feasible solution
  • The multiple optimal solution exist
  • a & b but not c

124 – In a transportation problem, when the number of occupied routes is less than the number of rows plus the number of columns -1, we say that the solution is:

  • Unbalanced.
  • Infeasible.
  • Degenerate.

125 – The only restriction we place on the initial solution of a transportation problem is that: we must have nonzero quantities in a majority of the boxes.

  • all constraints must be satisfied.
  • demand must equal supply.
  • we must have a number (equal to the number of rows plus the number of columns minus one) of boxes which contain nonzero quantities.

126 – The initial solution of a transportation problem can be obtained by applying any known method. However, the only condition is that

  • the rim condition are satisfied
  • the solution not be degenerate

127 – The dummy source or destination in a transportation problem is added to

  • satisfy rim condition

128 – The occurrence of degeneracy while solving a transportation problem means that

  • total supply equals total demand
  • the solution so obtained is not feasible

129 – An alternative optimal solution to a minimization transportation problem exists whenever opportunity cost corresponding to unused routes of transportation is:

  • positive and greater than zero
  • positive with at least one equal to zero
  • negative with at least one equal to zero

130 – One disadvantage of using North-West Corner Rule to find initial solution to the transportation problem is that

  • it is complicated to use
  • it does not take into account cost of transportation
  • it leads to degenerate initial solution

Operations Research Objective Questions with Answers Pdf Download

Leave a reply cancel reply.

Your email address will not be published. Required fields are marked *

  • View  PDF

Elsevier

Computers & Operations Research

Solving the yard crane scheduling problem with dynamic assignment of input/output points.

  • • Two efficient Greedy Randomized Adaptive Search Procedures (GRASP) for the YCSP.
  • • A novel constructive heuristic with new sequencing rules (SETR) and improved I/O assignment methods.
  • • New local search with greedy methods to save CPU time by avoiding I/O reassignments.
  • • Calibration with the Design Of Experiments (DOE) approach.
  • • Outperformance of the proposed methods against the state-of-the-art approaches.

Data availability

Cited by (0).

Operations Research

191. The large negative opportunity cost value in an unused cell in a transportation table is chosen to improve the current solution because

  • It represents per unit cost reduction
  • It represents per unit cost improvement
  • It ensure no rim requirement violation
  • None of the above

Correct answer: (A) It represents per unit cost reduction

192. The method of finding an initial solution based upon opportunity costs is called __________.

  • the northwest corner rule
  • Vogel's approximation
  • Johanson's theorem
  • Flood's technique
  • Hungarian method

Correct answer: (B) Vogel's approximation

193. The net cost of shipping one unit on a route not used in the current transportation problem solution is called the __________.

  • change index
  • Improvement index

Correct answer: (E) Improvement index

194. The objective function and constraints are functions of two types of variables, __________ variables and __________ variables.

  • Positive and negative
  • Controllable and uncontrollable
  • Strong and weak

Correct answer: (B) Controllable and uncontrollable

195. The objective function for a minimization problem is given by z = 2 x1 - 5 x2 + 3 x3 The hyperplane for the objective function cuts a bounded feasible region in the space (x1,x2,x3). Find the direction vector d, where a finite optimal solution can be reached.

  • d(-2,-5,-3)

Correct answer: (B) d(-2,5,-3)

196. The occurrence of degeneracy while solving a transportation problem means that

  • Total supply equals total demand
  • The solution so obtained is not feasible
  • The few allocations become negative

Correct answer: (B) The solution so obtained is not feasible

197. The only restriction we place on the initial solution of a transportation problem is that: we must have nonzero quantities in a majority of the boxes.

  • all constraints must be satisfied.
  • demand must equal supply.
  • we must have a number (equal to the number of rows plus the number of columns minus one) of boxes which contain nonzero quantities.

Correct answer: (A) all constraints must be satisfied.

198. The Operations research technique which helps in minimizing total waiting and service costs is

  • Queuing Theory
  • Decision Theory
  • Both A and B

Correct answer: (A) Queuing Theory

199. The procedure used to solve assignment problems wherein one reduces the original assignment costs to a table of opportunity costs is called __________.

  • stepping-stone method
  • matrix reduction
  • MODI method
  • northwest reduction
  • simplex reduction

Correct answer: (B) matrix reduction

200. The purpose of a dummy source or dummy destination in a transportation problem is to

  • prevent the solution from becoming degenerate.
  • obtain a balance between total supply and total demand.
  • make certain that the total cost does not exceed some specified figure.
  • provide a means of representing a dummy problem.

Correct answer: (B) obtain a balance between total supply and total demand.

Search MBA MCQ.com

COMMENTS

  1. 270+ Operations Research solved MCQs with PDF download

    Solved MCQs for Operations Research, with PDF download and FREE Mock test. Solved MCQs for Operations Research, with PDF download and FREE Mock test ... If the number of rows and columns in an assignment problem are not equal than it is called problem. A. balanced: B. unbalanced: C. infeasible: D. unbounded: Answer» B. unbalanced ...

  2. Operations Research MCQ [Free PDF]

    Get Operations Research Multiple Choice Questions (MCQ Quiz) with answers and detailed solutions. ... In linear programming, the feasible region represents all possible solutions that satisfy all the constraints of the problem, including both the inequality constraints and the non-negativity restrictions. The objective is to find the optimal ...

  3. PDF OPERATIONS RESEARCH Multiple Choice Questions

    a, b, and c are independent. a, b, and d are independent. d c. are independentb and d are i. dependent38. Consider the linear equation 2 x1 + 3 x2 - 4 x3 + 5 x4 = 10 How many basic and non. One variable is basic, three variables are non-basic. Two variables are basic, two variables are non-basic. e i.

  4. Operations Research Flashcards

    Operations research (OR) is an analytical method of problem-solving and decision-making useful in the management of organizations. In OR, problems are broken down into basic components and then solved in defined steps by mathematical analysis. Slack variable. In an optimization problem, a slack variable is a variable that is added to a less ...

  5. PDF OPERATIONS RESEARCH Multiple Choice Questions

    3. Operations management can be defined as the application of ----- -----to a problem within a system to yield the optimal solution. A. Suitable manpower B. mathematical techniques, models, and tools C. Financial operations 4. Operations research is based upon collected information, knowledge and advanced study

  6. Operations Research

    Multiple choice Questions on Operations Research. Practice for BBA or MBA exams using these MCQ. ... Operations Research. 1. Operations Research approach is _____. multi-disciplinary; ... An optimal assignment requires that the maximum number of lines which can be drawn through squares with zero opportunity cost should be equal to the number of

  7. Assignment Problem: Meaning, Methods and Variations

    After reading this article you will learn about:- 1. Meaning of Assignment Problem 2. Definition of Assignment Problem 3. Mathematical Formulation 4. Hungarian Method 5. Variations. Meaning of Assignment Problem: An assignment problem is a particular case of transportation problem where the objective is to assign a number of resources to an equal number of activities so as to minimise total ...

  8. Operations Research

    Multiple choice Questions on Operations Research. Practice for BBA or MBA exams using these MCQ. Page 3. ... An assignment problem is a particular case of _____. transportation Problem; assignment Problem; travelling salesman problem; replacement Problem; View answer.

  9. Operations Research Multiple Choice Flashcards

    Study with Quizlet and memorize flashcards containing terms like 1. Operations research is the application of _____ methods to arrive at the optimal Solutions to problems. A. Economical B. Scientific C. A and B both D. Artistic, 2. In operations research, the _____ are prepared for situations. A. Mathematical Models B. Physical Models Diagrammatic C. Diagrammatic Models, 3.

  10. Operations Research

    Multiple choice Questions on Operations Research. Practice for BBA or MBA exams using these MCQ. Page 4. ... Operations Research. 31. Using _____ method, we can never have an unbounded solution. ... The assignment problem is always a _____matrix. circle; square; rectangle; triangle;

  11. Assignment Model MCQ

    Get all study material quiz, articles, videos 🎥, notes 📝, problems and solutions at single click for Operations Research50 + Videos35 + Lessons40 + Solved...

  12. MCQ OR

    Mcq operations research multiple choice questions operations research is the application of to arrive at the optimal solutions to the problems. economical. Skip to document. University; ... An assignment problem can be solved by A. Simplex method B. Transportation method C. Both a &amp; b D. None of the above

  13. Operations Research Questions and Answers

    Operations Research Online Quiz Following quiz provides Multiple Choice Questions (MCQs) related to OS. You will have to read all the given answers and click on the view answer option. These HTML online test quizzes on Operations Research have answers available with pdf, which is very useful in interviews and also in HTML subject exams. Question 1: Operations… Read More »

  14. 300+ TOP Operations Research MCQs and Answers Quiz

    70 - While solving an assignment problem, an activity is assigned to a resource through a square with zero opportunity cost because the objective is to. Minimize total cost of assignment; Reduce the cost of assignment to zero; Reduce the cost of that particular assignment to zero; All of the above; MCQ on Operations Research

  15. Operations Research

    Multiple choice Questions on Operations Research. Practice for BBA or MBA exams using these MCQ. Page 13. MBA MCQ.com Search. ... In an assignment problem involving 5 workers and 5 jobs, total number of assignments possible are _____. 5; 10; 15; 20; View answer. Correct answer: (A) 5.

  16. MCQ OR

    An assignment problem can be solved by A. Simplex method B. Transportation method C. Both a & b D. None of the above. For a salesman who has to visit n cities which of the following are the ways of his tour plan A. n! B. (n+1)! C. (n-1)! D. n. The assignment problem A. Requires that only one activity be assigned to each resource B.

  17. Assignment MCQ [Free PDF]

    Get Assignment Multiple Choice Questions (MCQ Quiz) with answers and detailed solutions. ... Operations Research. Linear Programming. Assignment. Download Assignment MCQs Free PDF Assignment MCQ Quiz - Objective Question with Answer for Assignment - Download Free PDF ... An assignment problem is solved to minimize the total processing time of ...

  18. Operations Research

    Multiple choice Questions on Operations Research. Practice for BBA or MBA exams using these MCQ. Page 11. ... Operations Research. 101. All the basis for a transportation problem is _____. square; rectangle; ... Assignment Problem; Travelling salesman problem; Replacement Problem; View answer. Correct answer: (B)

  19. Solving the yard crane scheduling problem with dynamic assignment of

    For future research, we would like to explore local search in the assignment of I/O points in conjunction with the container sequence or in serialization with a variable neighborhood scheme. Further closing the gap between theory and practice, by bringing the problem even closer to reality, is a promising avenue of research.

  20. Operations Research

    Multiple choice Questions on Operations Research. Practice for BBA or MBA exams using these MCQ. ... The Operations research technique which helps in minimizing total waiting and service costs is ... Correct answer: (A) Queuing Theory. 199. The procedure used to solve assignment problems wherein one reduces the original assignment costs to a ...